![]() ![]() ![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
Pitch Preparation Glossary |
![]() |
Team Pages : Aus | Ban | Eng | Ind | NZ | Pak | SA | SL | WI | Zim | Non-test Playing | |||
Other Pages Introduction |
Home > Cricket > Pitch Preparation Introduction The quality and properties of a pitch used only for a limited overs match are vastly different to those for a five day test with respect to the thickness of the bulli, the drainage requirements, and the method of preparation. The purpose of this section is to present an abbreviated summary of the more important guidelines to inexperienced administrators on how to build cricket pitches for schools and clubs for use in limited over matches. Length of pitch The minimum length of established strips should be 24m. A slightly longer pitch (26m) has advantages but the sometimes recommended practice of shifting the crease along the length from match to match to avoid playing on the same deteriorated areas all the time often leads to unacceptable inconsistency in bounce and pace between the two ends of a pitch. Width of a pitch Each individual strip should be 3.05m wide. Directon of pitch Pitch length should be orientated to lie true north to south. Slope of oval Ideally, the oval should fall in all directions from the centre, but failing this, should have a single phase slope of 1% in any convenient direction. In the latter case, the pitch should be slightly raised to avoid problems of water draining onto or under the bulli. If the oval is on a very well drained soil no slope is required. Slope of pitch The slope of the pitch should not exceed 1% and it should follow the slope pattern of the oval. If the oval is centre sloped, the pitch square should also slope from the centre. The amount of fall should therefore not exceed 30mm across a 3.05m strip or 200mm along its length, being as flat as possible at the centre. Height of pitch above outfield The pitch square should be about 75mm above the level of the outfield to allow for surface drainage off the pitch. Drainage The material underlying the pitch should allow for good drainage and artificial drains might need to be installed to ensure that any water entering the sub-base will be able to drain away freely. If evapotranspiration is the only way in which water is lost from the pitch area, salts will accumulate in the bulli layer. Amongst other undesireable effects, this will promote crumbling of the pitch surface. It is preferable to include at least one gravel layer as a sub-base, even if the underlying material allows for free drainage. An artificial drainage system (e.g. pipes) is recommended if there is any indication of poor drainage. These drain pipes should be installed at a slope of 1 : 100 to quickly remove all the water from the sub-base of the pitch and the outfield. Controlling invasion To prevent grass from the outfield invading the pitch, 40cm wide black plastic strips should be laid vertically at the edges of the excavation before filling. The plastic will also assist in preventing water entering the pitch area from its surrounds. Excavation Excavate to the desired size and depth. Decide on the number of layers to be included and their depths, and from this total subtract 75mm to allow the finished pitch to lie slightly above the outfield level. Generally, pitches for five-day matches need to be excavated to a depth of 550mm (including gravel layers) below final height; 475mm for three-day matches (again including gravel layers); and for one-day matches 400mm ( where gravel is being used) or 225mm (with no gravel layers). These depths are the minimum depth at the upper-slope edge of the pitch area, and if a layer of clay loam is to be used, the depth of this layer must be added to the above values. Base Construction Irrespective of the drainage capacity of the underlying material, the excavated base should be inclined in the direction of natural drainage. A ring drain should be constructed on the perimeter of the excavation to remove all excess water from the pitch area. In well drained soils a coarse gravel drain will suffice, but in poorly drained soils drainage pipes may be required and a more sophisticated system of lateral pipe-drains designed to drain the entire base. 1. Excavate the trenches for the drain pipes, making sure of a fall of
at least 1 : 100, and line the trenches with geotextile (e.g. Bidum). Drain pipes with a
diameter of 50mm are laid on a thin layer of coarse sand and the trenches are backfilled with
the same sand. CRUSHED GRANITE SHOULD NEVER BE USED for this as it forms a hard layer which
severly restricts water movement. The bulli 1. The selected bulli should be dry and the finer it is, the better. The
best mixture is one which contains 40% of aggregates less than 2mm in diameter, with about
60% less than 5mm. It must be free of stones, root material and other impurities. 2. Where moles are likely to pose a problem, a 50mm layer of crushed
glass can be laid immediately below the bulli. 3. Before laying the bulli, it should be air-dried and rolled on a hard surface (e.g. a car park) to ensure a degree of uniformity in particle size. This also allows an oportunity to remove stones, roots and other unwanted debris. Do not seive the bulli. 4. Add 100mm of appropriately fertilised bulli and compact in a dry condition with a roller or vibrator. Score the surface. 5. The construction can then be completed by infilling to the surface
with layers of bulli, each not more than 100mm thick. On each occasion the bulli must be
compacted and its surface scored before any additional material is added. Grass establishment 1. Soak the total area before planting. All hollows and sagged areas
should be filled. The grass should be planted only when the surface is dry enough to walk on
without having clay stick to ones shoes. The planted area should be watered at least once a day with a fine nozzle sprayer until there are signs of sprouting. Daily watering should continue until the grass has covered at least 75% of the area. A light dressing of dry bulli can then be spread over the pitch and levelled with a straight edge. Post-construction maintenance The grass should initially be allowed to grow out (to about 30mm) so that it can develop a good root system. Once it has reached full cover, its height can be reduced to 15mm.
Home | About | New ! | Sitemap Best viewed in 800 x 600 resolution Internet Explorer 6.0 and above. |